Disabling tasks and schedules
In Varicent Incentives, you can prevent schedules, or tasks within a schedule, from running.
In the Scheduler module, place your cursor over the task or process that you want to disable and click the more options (...) menu
Select Edit.
You can also select Skip next run to disable tasks and schedules for next scheduled run only. After the next scheduled run, the task or schedule is automatically enabled again.
Click Edit task / Edit folder toggle icon to disable tasks and schedules.
Note
A task or process that is disabled cannot be run manually or within a scheduled process until it is enabled again. It can be useful to disable a task or process when you do not want a certain task within a process, such as a saved import, to run.